Progress Update 5/9

Crews continue to install exterior materials.  The east building materials are complete and the west building’s materials are approximately 50% complete.

Progress continues in the east building: Units 1 has been painted and the kitchen back splash is installed. Unit 2 is prepping for paint.  Cabinets are installed through unit 5, and are stocked and ready for installation in unit 6.  Bathroom tile is complete through unit 6, and is in progress in units 7 and 8.  Crews have started to install batt insulation in unit 9.

Rough MEP continues in the west building. Unit 1 draftstop insulation is complete and batt insulation has begun.

 