Progress Update 5/17

West Building –

The electrician is progressing though the units.  In Unit 1, they were stocking drywall and insulation was complete. Batt insulation was in progress in Unit 2 and draftstop insulation will be starting in unit 3.

 

East Building –

Lots of exciting progress here – Unit 1 has appliances and bathroom fixtures installed. The kitchen backsplash was installed in Unit 2.  Painters were prepping for paint in Unit 4. In Unit 9, drywall is installed and tape and mud will start next.