Construction Progress Update 6-27-17

Exterior paint continues and is approximately 60% complete on the east building.  Crews will be starting the prep work for concrete pathways this week.

 

In 2733:

Unit 1 – Carpet is scheduled to be installed this week.  Electrical trim work and HVAC work is in progress.

Unit 2 – Carpet is complete.  Electrical trim work and HVAC work is in progress.

Unit 3 – Carpet is complete.  Electrical trim work and HVAC work is in progress.

Unit 4 – Carpet is scheduled to be installed this week Electrical trim work and HVAC work is in progress.

Unit 5-8  – Electrical, Plumbing, and HVAC trim work is in progress

Unit 9 – Cabinets are now set, countertop templating is scheduled to be completed this week and installation is scheduled for next week.  Interior paint is also scheduled.

 

In 2741 –

Unit 1 – Hardwood is installed. Bathrooms are ready for tile.

Unit 2 – Tile is being installed in the bathrooms and looks great!

Unit 3 – Bathrooms are ready for tile.

Unit 4 – Drywall mud and tape is in progress and bathrooms are ready for tile.

Units 5-9 – Drywall will continue to progress down the line for these units.

 