Progress Update 7-26

Progress continues at Twin 9s! The exterior is looking great with paint complete on both buildings, and the front walkway concrete complete.

In the east building, the units continue to progress, with the first four units being the most complete. Units 5-9 continue to progress with plumbing, lighting, appliance delivery.

In the west building, tile crews and drywall crews are making considerable progress. Tile is in progress or complete through unit 5 and drywall mud and tape is complete through unit 7 with crews working on mud and tape in unit 8.  Drywall installation is nearing completion in unit 9.